Proposed Project Schedule 2021–24

  • January – August 2021

    • Project Scope Determination

    Oct. 12, 2021

    • Referendum/SEQRA Resolution
      Requires Board Resolution for Project Scope and Finances

    October — December 2021

    • 45 Day Public Notice
      Public Meeting/Campaign

    Dec. 7, 2021

    • Referendum Vote
      Held at North Street School

    January — September 2022

    • Design and Construction Documents

    September 2022 — February 2023

    • SED Review & Approval
      Assumes Six Month Review Period, Comments, Approval

    February — March 2023

    • Bid & Award

    April 2023 — August 2024

    • Construction
      Assumes Two Summer Construction Phasing

    December 2024

    • Final Inspection & Closeout