January – August 2021
- Project Scope Determination
Oct. 12, 2021
- Referendum/SEQRA Resolution
Requires Board Resolution for Project Scope and Finances
October — December 2021
- 45 Day Public Notice
Public Meeting/Campaign
Dec. 7, 2021
- Referendum Vote
Held at North Street School
January — September 2022
- Design and Construction Documents
September 2022 — February 2023
- SED Review & Approval
Assumes Six Month Review Period, Comments, Approval
February — March 2023
- Bid & Award
April 2023 — August 2024
- Construction
Assumes Two Summer Construction Phasing
December 2024